BSB/EB – Heating Hot Water Outage February 27

Heating hot water service to the BSB and EB will be shut down from 7:00 a.m. until 4:00 p.m., on Wednesday, February 27, 2019, for leak repairs.  The outage will affect comfort heating to both the BSB and EB.  For additional information, contact the Facilities Service Center at 458-4262.

 


XL/XAG – Parking Spaces and Driving Aisles Closed Between March 7 and March 24

Parking spaces and driving aisles in the Ximenes Avenue Lot (XL) and the Ximenes Avenue Garage (XAG) will be closed for tie-in of the new Science and Engineering Building (SEB) to the South Thermal Energy Plant (STEP) as follows:

 XL Lot & XAG Garage Closures:

 

 Dates:  Location:  Purpose:
XL – driving aisle & 22 parking spaces 3/7/2019  – 3/17/2019 West of XAG Staging of piping and plumbing materials and crane set up
XL – driving aisle & 4 parking spaces 3/11/2019 – 3/14/2019 South of XAG Delivery and installation of new chiller and crane set up
XAG – entire top level 3/11/2019 – 3/17/2019 Top level of XAG Lift piping and plumbing materials to top of XAG
XAG – 10 parking spaces on top level 3/7/2019 – 3/24/2019 Top level of XAG Preparation and installation of new piping & plumbing

Garage detour signage will be posted in and around the XAG and temporary barricades and construction tape will be placed around the parking and driving aisle closures. For additional information, reference the attached map or contact the Facilities Service Center at 458-4262.

XAG Closures for South Thermal Plant Work

 


XL: Portion of Parking Lot Aisle Closed March 1 and March 15

A portion of the Ximenes Avenue Lot (XL) parking aisle, adjacent to the South Thermal Energy Plant (STEP), will be closed from 4:00 a.m. on March 1, 2019 until 7:00 a.m. on March 2, 2019 and from 4:00 a.m. on March 15, 2019 until 7:00 a.m. on March 16, 2019, for slab pours. A slab for a 2000-ton chiller will be poured south of the STEP and a slab for a transformer will be poured east of the Ximenes Avenue Garage (XAG). Barricades, construction tape and a concrete truck placed along the aisle closure during both pours will be removed by 7:00 a.m. on March 2nd and March 16th. For additional information, reference the attached map or contact the Facilities Service Center at 458-4262.

XAG Concrete Slab Pours


BSE: Steam Outage Scheduled for February 21

Steam service to the BSE will be shut down from 7:00 a.m. until 4:00 p.m. on Thursday, February 21, 2019, for leak repairs. The outage will affect non-potable and potable domestic hot water, auto claves, tunnel washers and building humidity. For additional information, contact the Facilities Service Center at 458-4262.


AET/BSE – No Hot Water Service and Increased Humidity Levels Until Noon Feb 4

The sprinkler system in the Ximenes Avenue Garage (XAG) was activated by this morning’s mechanical fire. Facilities has turned the sprinklers off and is making necessary repairs before recharging the system. During this time, there will be no hot water and increased humidity levels at the AET and BSE. Humidity levels are expected to return to normal and hot water service restored by no later than noon today, February 4. For additional information, contact the Facilities Service Center at 458-4262.


CC Update: Installation of New Air Handler Unit – Crane Placed on Southwest Corner of CC May 8

Update 5/3/19: A crane will be placed on the exterior southwest corner of the building, from 7:00 a.m. until 2:00 p.m. on May 8, 2019, to assist with project materials/debris removal. For additional information, reference the updated attached map.

Work to install a new air handler unit in the Convocation Center (CC) is scheduled to begin on February 15, 2019 and go through May 3, 2019.  Two cranes and a construction truck will be placed on the exterior south side of the building until approximately March 18, 2019, to assist with equipment mobilization and debris removal.  For additional information, reference the attached map or contact the Facilities Service Center at 458-4262.

2018502 UTSA FY-18 – Crane Lift Locations_May_2019


FLN Collaborative Space Project Begins Feb 11

The FLN Collaborative Space project is scheduled to begin on February 11, 2019 and go through March 15, 2019.  Work includes the use of ladders and scaffolding to access the ceiling, run conduit and raceway and replace light fixtures in the third floor corridors.  For additional information, reference the attached floor plan or contact the Facilities Service Center at 458-4262.

3rd Floor FLN Area of Work PP21818902