Road repairs to a large portion of Main Campus roads will occur from July 19 through August 23, 2019, to include asphalt replacement, seal coating of road surfaces, and painting/striping. Work will be performed each day between 7:00 a.m. and 8:00 p.m. or 10:00 p.m. to 7:00 a.m., Monday – Sunday.

Repairs will require intermittent road and lane closures throughout the duration of the project. We have developed a work schedule to minimize the disruption to traffic flow and will have barricades, signs, and flagmen onsite to identify detours.

Work will be accomplished in two phases. Road repairs are scheduled from July 19 to August 3, 2019 and seal coating and painting/striping will occur from July 25 to August 23, 2019. Please refer to the attached maps and schedules to see when particular portions of the Main Campus roads will be closed.

As with any construction project, there is a possibility that the schedule will need to be adjusted due to weather or unforeseen circumstances. We will post any changes to the schedule on the Facilities website at https://facilities.utsa.edu/announcements/main-campus-road-repairs-july-19-august-23/, through Facilities email notifications, and via UTSA social media platforms.

For additional information, please contact the Facilities Service Center at 458-4262 or FacilitiesServiceCenter@utsa.edu.

Update 9:  8/21/2019 – Road repairs have been completed ahead of schedule and all campus roads are open.  

Update 8:  8/16/2019 – Additional road repair added to the schedule.  Road repair on Barshop Blvd., from UTSA Blvd. to Barshop Circle, will occur from 21 Aug to 22 Aug.  This portion of Barshop Blvd. and entrance to campus from UTSA Blvd. will be closed.  Please refer to the Seal Coat Schedule and Map below.   

Update 7:  8/13/2019 – Changes to the Traffic Impact section of the Seal Coat Schedule (Areas 6 & 11) and to announce that BR3 lot will be closed when Area 6 is seal coated from 15 Aug to 17 Aug.  

Update 6:  8/12/2019 – We are ahead of schedule due to the great weather that we are having in San Antonio.  To keep the momentum going, we are accelerating the final two phases of the project.   Areas 4b, 7a, and 7b begin today, 8/12/2019.  Areas 6 and 11 will occur 15-17 August.  Changes are reflected in the link below and annotated with an asterisk.   

Update 5:  8/6/2019 – Additional changes to the Seal Coat Schedule and Map dated 8/1/2010  Changes are reflected in the link below and annotated with an asterisk (*). 

UPDATE 4:  8/1/2019 – Additional changes to the Seal Coat Schedule and Map dated 7/26/2019.  Changes are reflected in the link below and annotated with an asterisk (*).  

UPDATE 3:  7/26/2019 – Seal coat work on areas 1 & 5 will begin on Monday, July 29, 2019 instead of the original posted date of July 30, 2019.  This change is reflected in the link below and annotated with an asterisk (*).  

UPDATE 2:  7/25/2019 – Additional changes to the Seal Coat Schedule and Map published on 7/19/2019 and 7/24/2019.  Changes are reflected in the link below and annotated with an asterisk (*).  

UPDATE 1:  7/24/2019 – Some changes were made to the Seal Coat Schedule and Map first published on 7/19/2019.  Changes are reflected in the link below and are annotated with an asterisk (*).   

Asphalt Repair Schedule and Map: Jul 19-Aug 3

Seal Coat Schedule and Map: Jul 25-Aug 19