Project Details


Substantial Completion

June, 2020

Total Projected Cost

$95,000,000

Square Footage

140,000 GSF

Architects

Alamo Architects

San Antonio, TX

TreanorHL

Lawrence, KS

Engineers

Shah Smith & Associates, Inc.

Houston, TX

Contractors

Bartlett Cocke General

Contractors, San Antonio, TX

Summary:  The project consists of approximately 140,000 gross square feet spread across four stories. The building will provide for classrooms, faculty offices, and science and engineering research and instructional laboratories, and is part of the University’s strategic plan for providing state-of-the-art space for Science, Technology, Engineering and Mathematics (STEM) education and research.

Location:  Adjacent to the Paseo del Sur on the southeast portion of campus, east of the Biotechnology Sciences and Engineering (BSE) Building and south of the Arts (ART) Building.

SEB Fact Sheet

SEB Construction Updates 

May 7, 2019 – Project Closures Starting May 17, 2019

A portion of the Paseo del Sur, approximately one hundred and ten parking spaces (110) at the north end of the Bauerle Road Lot 1 and the sidewalk from Bauerle Road Lot 1 to key Circle will be closed beginning May 17, 2019, for paver, roadway, parking and sidewalk work as part of the Science and Engineering Building (SEB) project.

The Bauerle Road Lot 1 parking spaces will be closed from May 17, 2019 through August 18, 2019 and a portion of the Paseo del Sur will be closed from May 20, 2019 through June 30, 2019.

The Bauerle Road Lot 1 sidewalk will be closed from June 17, 2019 through August 18, 2019. The closures will be fenced off with chain-linked fencing and construction signage will be posted in and around the closures to assist with detours.

For additional information, please reference the attached maps or contact the Facilities Service Center at 458-4262

SEB – Paseo del Sur and BR Lot 1 Closure

SEB – BR Lot 1 and Bauerle Rd Sidewalk Closure

May 7, 2019 – Removal of Tower Crane May 17-19, 2019

The tower crane that was temporarily set up at the Science and Engineering Building (SEB) project site will be disassembled and removed, weather permitting, between 7:00 a.m. on Friday, May 17, 2019 and 5:00 p.m. on Sunday, May 19, 2019.  Construction vehicles may affect traffic in and around the job site.  For additional information, please contact the Facilities Service Center at 458-4262.

PHOTO GALLERY

March 28, 2019

March 28, 2019

January 7, 2019

January 7, 2019

November 2, 2018

November 2, 2018

October 4, 2018

August 1, 2018

August 1, 2018

August 1, 2018

May 10, 2018

Aerial Photo of the SEB – April 23, 2018

Construction Activity – December 8, 2017

Tower Crane On Site – November 30, 2017

SEB Foundation Work – November 20-24, 2017

SEB Foundation Work – October 23-27, 2017

SEB Utility and Foundation Work – October 2-6, 2017

SEB Utility and Foundation Work – September 4-8, 2017

Aerial Photo – July 2017

Utility Work for SEB – August 7 – 11, 2017

Utility Work at SEB Site – July 10 – 14, 2017 

Utility Work at SEB Site – June 26 – 30, 2017

Utility Work at SEB Site – June 12 – 17, 2017

SEB Ground Breaking Ceremony – June 9, 2017

Future Site of SEB (Utility Work Began on June 5, 2017)