Project Details


Substantial Completion

June, 2020

Total Projected Cost

$95,000,000

Square Footage

140,000 GSF

Architects

Alamo Architects

San Antonio, TX

TreanorHL

Lawrence, KS

Engineers

Shah Smith & Associates, Inc.

Houston, TX

Contractors

Bartlett Cocke General

Contractors, San Antonio, TX

Summary:  The project consists of approximately 140,000 gross square feet spread across four stories. The building will provide for classrooms, faculty offices, and science and engineering research and instructional laboratories, and is part of the University’s strategic plan for providing state-of-the-art space for Science, Technology, Engineering and Mathematics (STEM) education and research.

Location:  Adjacent to the Paseo del Sur on the southeast portion of campus, east of the Biotechnology Sciences and Engineering (BSE) Building and south of the Arts (ART) Building.

SEB Fact Sheet

SEB Construction Updates 

November, 6, 2018 – SEB Related Intermittent Closures Continue Through November 28, 2018

The north BSE loading dock and walkway that link to the Paseo del Sur and the BSE/EB covered walkway located below the plaza level will continue to be intermittently closed through November 28, 2018, for installation of overhead chilled and heating hot water pipes. Scissor lifts will be used to perform the installations and flag and spotter personnel will be used to assist with vehicular and pedestrian traffic. Work will not affect access to the BSE and EB. For additional information, reference the attached drawing or contact the Facilities Service Center at 458-4262.  Periodic Closures North of BSE Thru 11_28_2018

August 13, 2018 – Paseo del Sur Closure Continues Through December 31, 2018

The partial closure of the Paseo del Sur (Paseo) will continue through December 31, 2018, as part of the ongoing construction of the new Science and Engineering Building (SEB) and the installation of a bridge that will connect the SEB to the west side of the Paseo. During the closure, there will not be a continuous route along the Paseo del Sur from the Ford Avenue Lot bus stop to the ART and EB, as well as the staircase between the ART and FLN. Pedestrians will need to detour through the AET, BSE and EB alternate walking paths. A temporary sidewalk will be installed to supplement the primary path and signage will be used to assist with detours. For additional information, please reference the attached drawing or contact the Facilities Service Center at 458-4262.  Paseo del Sur Shutdown Graphic

PHOTO GALLERY

November 2, 2018

November 2, 2018

October 4, 2018

August 1, 2018

August 1, 2018

August 1, 2018

May 10, 2018

Aerial Photo of the SEB – April 23, 2018

Construction Activity – December 8, 2017

Tower Crane On Site – November 30, 2017

SEB Foundation Work – November 20-24, 2017

SEB Foundation Work – October 23-27, 2017

SEB Utility and Foundation Work – October 2-6, 2017

SEB Utility and Foundation Work – September 4-8, 2017

Aerial Photo – July 2017

Utility Work for SEB – August 7 – 11, 2017

Utility Work at SEB Site – July 10 – 14, 2017 

Utility Work at SEB Site – June 26 – 30, 2017

Utility Work at SEB Site – June 12 – 17, 2017

SEB Ground Breaking Ceremony – June 9, 2017

Future Site of SEB (Utility Work Began on June 5, 2017)