
Project Details
Substantial Completion
June, 2020
Total Projected Cost
$95,000,000
Square Footage
140,000 GSF
Architects
Alamo Architects
San Antonio, TX
TreanorHL
Lawrence, KS
Engineers
Shah Smith & Associates, Inc.
Houston, TX
Contractors
Bartlett Cocke General
Contractors, San Antonio, TX
Summary: The project consists of approximately 140,000 gross square feet spread across four stories. The building will provide for classrooms, faculty offices, and science and engineering research and instructional laboratories, and is part of the University’s strategic plan for providing state-of-the-art space for Science, Technology, Engineering and Mathematics (STEM) education and research.
Location: Adjacent to the Paseo del Sur on the southeast portion of campus, east of the Biotechnology Sciences and Engineering (BSE) Building and south of the Arts (ART) Building.
SEB Construction Updates
- June 12, 2019 – News 4 SA tours SEB on UTSA Main Campus to view progress
- May 24, 2019 – Milestones signify progress of new UTSA Science and Engineering Building
- May 7, 2019 – Project Closures Starting May 17, 2019
- May 7, 2019 – Removal of Tower Crane May 17-19, 2019
- August 13, 2018 – Paseo del Sur Closure Continues Through December 31, 2018
- November 6, 2018 – SEB Related Intermittent Closures Continue Through November 28, 2018
- October 25, 2018 – Update to the August 15, 2018 post
- August 15, 2018 – SEB Related Intermittent Closures August 20-November 11, 2018
- June 5, 2018 – Paseo del Sur and Path Closures June 11 – December 31
- June 1, 2018 – SEB construction featured on NEWS4SA.com
- May 25, 2018 – SEB construction featured on UTSA Today
- May 1, 2018 – Construction Update
- February 13, 2018 – Common Area Furniture Review
- December 6, 2017 – Parking Space and Sidewalk Closures
- November 20, 2017 – Parking Spaces Reopen
- SEB Construction Update – August 8, 2017 – Fall Semester
- 21 June, 2017 – Construction Challenges – Closed Service Drive and Pedestrian Route
- SEB Construction Begins 5 June, 2017 – Multiple Closures
- SEB Constrution ADA Route
PHOTO GALLERY
August 21, 2020 (SEB completed)
May 8, 2020
May 8, 2020
April 9, 2020
April 9, 2020
April 9, 2020
April 9, 2020
November 25, 2019
November 25, 2019
November 25, 2019
July 19, 2019
July 19, 2019
May 29, 2019
May 29, 2019
March 28, 2019
March 28, 2019
January 7, 2019
January 7, 2019
November 2, 2018
November 2, 2018
October 4, 2018
August 1, 2018
August 1, 2018
August 1, 2018
May 10, 2018
Aerial Photo of the SEB – April 23, 2018
Construction Activity – December 8, 2017
Tower Crane On Site – November 30, 2017
SEB Foundation Work – November 20-24, 2017
SEB Foundation Work – October 23-27, 2017
SEB Utility and Foundation Work – October 2-6, 2017
SEB Utility and Foundation Work – September 4-8, 2017
Aerial Photo – July 2017
Utility Work for SEB – August 7 – 11, 2017
Utility Work at SEB Site – July 10 – 14, 2017
Utility Work at SEB Site – June 26 – 30, 2017
Utility Work at SEB Site – June 12 – 17, 2017
SEB Ground Breaking Ceremony – June 9, 2017
Future Site of SEB (Utility Work Began on June 5, 2017)