Announcement:

The Office of Facilities invites the UTSA community to take a customer satis ... (Read More)

Project Details


Substantial Completion

June, 2020

Total Projected Cost

$95,000,000

Square Footage

140,000 GSF

Architects

Alamo Architects

San Antonio, TX

TreanorHL

Lawrence, KS

Engineers

Shah Smith & Associates, Inc.

Houston, TX

Contractors

Bartlett Cocke General

Contractors, San Antonio, TX

Summary:  The project consists of approximately 140,000 gross square feet spread across four stories. The building will provide for classrooms, faculty offices, and science and engineering research and instructional laboratories, and is part of the University’s strategic plan for providing state-of-the-art space for Science, Technology, Engineering and Mathematics (STEM) education and research.

Location:  Adjacent to the Paseo del Sur on the southeast portion of campus, east of the Biotechnology Sciences and Engineering (BSE) Building and south of the Arts (ART) Building.

SEB Fact Sheet

SEB Project Update – December 6, 2017

Nineteen (19) parking spaces in the Bauerle Road Lot 1 will be closed from December 15, 2017 until June 17, 2020. The temporary sidewalk located along Bauerle Road will also be closed from December 15, 2017 until January 7, 2018. For additional information please reference the attached drawing.

SEB Supplemental Closures Map

SEB Project Update – November 20, 2017

Forty-five (45) parking spaces in the Ximenes Avenue Lot will reopen on November 30, 2017.  Twenty (20) parking spaces in the Ford Avenue Lot will be closed for repaving beginning November 30, 2017 and will reopen on January 7, 2018.

SEB Construction Update – August 8, 2017

Construction of the new Science and Engineering Building (SEB) continues through the start of the fall semester.  The greenbelt east of the BSE and adjacent to the ART, service drive entrance at the ART, and portions of Bauerle Road Lot 1, Ford Avenue Lot, and Ximenes Avenue Lot remain closed.  Beginning August 21, 2017, access to Paseo del Sur via south of campus, nineteen additional parking spaces in the Bauerle Road Lot 1, and twelve additional parking spaces in the Ford Avenue Lot will be available.  Pedestrian signage including directional, detour and alternate ADA route, to and from the plaza level via the ART elevators, have been installed throughout the construction site.  Temporary sidewalks have also been installed along Bauerle Road, between the ART and Paseo del Sur, to assist with pedestrian detours.  All closures will remain cordoned off with construction fencing.  For additional information, please reference the attached map or contact the Facilities Service Center at 458-4262.

SEB Construction Map – August 21, 2017 to January 7, 2018

Location of Closure: Date of Closure:
Greenbelt – construction site June 5, 2017 – June 17, 2020
Bauerle Rd Lot 1 June 5, 2017 – June 17, 2020
Service drive entry – next to ART June 5, 2017 – January 7, 2018
Ximenes Ave and Ford Rd lots – next to AET June 5, 2017 – January 7, 2018
Ford Rd Lot (portion) – next to BSE June 1, 2017 – January 7, 2018

Update – 21 June, 2017 – Construction Challenges – Closed Service Drive and Pedestrian Route

SEB Construction Begins 5 June, 2017 – Multiple Closures

SEB Constrution ADA Route

PHOTO GALLERY

 

Construction Activity – December 8, 2017

Tower Crane On Site – November 30, 2017

SEB Foundation Work – November 20-24, 2017

SEB Foundation Work – October 23-27, 2017

SEB Utility and Foundation Work – October 2-6, 2017

SEB Utility and Foundation Work – September 4-8, 2017

Aerial Photo – July 2017

Utility Work for SEB – August 7 – 11, 2017

Utility Work at SEB Site – July 10 – 14, 2017 

Utility Work at SEB Site – June 26 – 30, 2017

Utility Work at SEB Site – June 12 – 17, 2017

SEB Ground Breaking Ceremony – June 9, 2017

Future Site of SEB (Utility Work Began on June 5, 2017)